Superior Asphalt will begin mill and overlay road work in the following areas of The Villages based on the schedule below:

Community Development District 4

  • Unit 62 3/19/26 – 3/31/26
  • Unit 63 3/30/26 – 4/9/26
  • Unit 64 4/8/26 – 4/15/26

Community Development District 2

  • El Santiago VRC 4/14/26 – 4/19/26

Spanish Springs – Night Work

  • Main St 4/19/26 – 4/20/26
  • Caballero Ct 4/21/26 – 4/21/26
  • Lake Sumter Landing – Night Work
  • Bailey Cotton Parking Lot 4/22/26 – 4/22/26
  • Lake Shore Dr 4/23/26 – 4/27/26

This schedule may be adjusted due to unforeseen circumstances, including weather.

If you have any questions during the work, there will be someone on site to assist you. For additional information, contact District Property Management at (352) 753-4022.