During the month of February, underground stormwater pipes will be repaired in certain areas of Community Development Districts 1 and 2 in The Villages by Vacvision Environmental. The stormwater pipe repair project will be completed in two phases.
The Phase One Schedule is as follows:
From Feb. 2 to 6
• Enrique Drive
• Camero Drive
• Galindo Place
• Augustine Drive
• Cardona Way
• Castano Place
• Morse Boulevard
• Mareno Court
From Feb. 9 to 13
• El Camino Real
• Morse Boulevard
• Chaparral Drive
• Privada Drive
The Phase 2 portion of the project will begin after mid-February and a separate notice will be provided for this phase.
The utilization of signage, flagging personnel and traffic channeling devices will aid motorists hrough the construction areas but please exercise caution. Some minor delays can be expected during the scheduled times.
Questions or concerns can be directed to Sumter County Public Works Division (352) 689-4400